Contract Title |
Description of Works |
Client |
Approx Value SR |
Contract Completion |
Riyadh Electrical Co. – 7th Stage Works |
Installation and Jointing of Underground Electric 33kV, 13.8kV LV Cables and Sub-Station |
SCECO Central - Riyadh |
11.0M |
1978 |
Seven Slaughter Houses |
Supply and installation of Electrical Services |
Ministry of Interior, Riyadh |
12.0M |
1978 |
Sealand Container Terminal, Dammam |
Supply and installation of Electrical and Mechanical Services |
Sealand/Rezayat |
4.0M |
1978 |
Royal Places Riyadh. 13.8kV Network Reinforcement |
Installation of 13.8kV XLPE underground cables, jointing and telecommunications. |
Ministry of Finance and National Economy |
2.0M |
1979 |
Palace of H.M King Khalid- Riyadh. LV Network Reinforcement |
Supply, Installation and Commissioning LV Cables and Switchgear |
H.M King Khalid |
2.0M |
1980 |
Riyadh Electric Co. Unified rates 1979/80 |
Installation of Underground Electric HT/LT Cables and Sub-station erection |
SCECO Central Region, Riyadh |
19.0M |
1980 |
Madina Electric Co. Cable Jointing Works |
Supply and Services of Cable Jointers to carry out 33kV & 15kV Cable Jointing |
Madina Electric Company |
3.0M |
1979 |
National Commercial Bank, Khalidia Branch, Jeddah Conversion |
Design, Supply and Installation of Electrical and Mechanical Services including Air Conditioning, Ventilation, Plumbing and Fire Control System |
Saudi Tarmac Ltd. and National Commercial Bank |
1.8M |
1981 |
Riyadh Electric Company Contract No. 421/1400/A |
Installation of 8.6KM of 132kV S/C Oil filled Cables and Pilot Cables, Joint Bays Pressure Tank Chambers and link box pits together with associated civil works |
Mitsui & Co Ltd. Japan and SCECO Riyadh |
4.5M |
1981 |
Contract No. 596-C01. Royal Commission for Jubail and Yanbu |
Procurement and Construction of Community Telephone Cable Network-Phase K |
Royal Commission for Jubail and Yanbu |
35.4M |
1982 |
Riyadh Electric Co., Cable Jointing |
Supply of Services for 132kV and 33kV |
SCECO Central Region, Riyadh |
1.8M |
1982 |
Abdul Latif Office Building, Jeddah |
Design, supply and installation of Electrical, Plumbing and Air Conditioning services in 12 Store Building |
Saudi Tarmac Ltd./ Abdul Latif |
3.4M |
1982 |
Contract No. 710-C02, Royal Commission for Jubail and Yanbu |
Supply and Installation of Underground Electric HT/LT Cable HT/LT transformers and switchgear and telephone cable and equipment |
Saudi Tarmac Ltd., Royal Commission for Jubail and Yanbu |
21.6M |
1982 |
Riyadh Electric Co. United Rates 1980/81 |
Installation of Underground Electric 33kV and 13.8kV cables and substation erection |
SCECO Central, Riyadh |
30.0M |
1982 |
Academic Campus. Stadium King Abdul Aziz Military Academy. Riyadh |
Supply and installation of Electrical Services |
International Contractors Group/Johnson Bros. Corp. (Joint Venture) |
13.0M |
1982 |
SCECO Jeddah. Laying of HT & LT Cables and House Connections |
Installation of HT & LT Underground cables together with associated civil works and house connections |
SCECO Western Region, Jeddah |
30.0M |
1982 |
National Methanol Co., Jubail |
Installation of Temporary Electrical construction power and underground water sewage and compressed air utilities |
Saudi Braun, Jubail |
1.3M |
1982 |
Electrical and Mechanical Services, Jeddah Ship Repair Yard and Associated Accommodation Compound |
Design, Supply and Installation of Electrical and Mechanical services including Air Conditioning and Plumbing Works (Total 10 Buildings) |
Saudi Tarmac Ltd. Saudi Arabian Ports Authority |
12.0M |
1982 |
A.C.E. Housing Compound |
Installation of 13.8kV Distribution system. External lighting, Plumbing and potable water installation |
Al Esayi Saif Noman Douglas Co. Ltd., Jeddah |
5.0M |
1982 |
Fuel Facilities Area 19F King Khalid Military City |
Supply and Installation of Mechanical, Electrical and Instrumentation works |
SADCO/KIER International, Joint Venture |
30M |
1983 |
Riyadh Electric Co. Contract No. 366/02 |
Installation of 20.5KM of 132kV Oil Filled cables, Joint Bays, Pressure Tank Chambers and link box pits together with associated civil works |
Mitsui & Co. Ltd. Japan and SCECO |
7.0M |
1983 |
Canadian Embassy Riyadh |
Supply and Installation of Electrical and Mechanical services including Air Conditioning, Ventilation Plumbing, Fire Protection and Irrigation |
Laing Wimpey Ali Reza Limited & Canadian Government |
12.0M |
1984 |
Al Amal Hospital. Operating Theater Suites |
Installation only of Mechanical and Electrical services including Air Conditioning, Ventilation, Plumbing and Compressed Air. |
Grundi Controlled Environments Ltd. |
0.4M |
1984 |
Port of Dammam, Security Surveillance System |
Installation of CCTV Cables into existing duct banks to various camera locations throughout the port complex |
EASAMS Limited |
0.5M |
1984 |
Riyadh Electric Co. Contract No. 0675/03 |
Installation of 18kM of 132kV Oil Filled Cable, Joint Bays, Pressure Tank Chambers. Link Box pits together with all associated civil works including concrete duct banks |
Mitsui & Co. Ltd. Japan and SCECO Riyadh |
3.4M |
1984 |
Central Control and Monitoring System at King Khalid Military City, Hafr Al Batin |
Supply and Installation of CCMS Cables into underground duct banks and control buildings |
Honeywell Turki Arabia Ltd., US Army Engg Division, Middle East |
8.0M |
1986 |
Binzagr Lever limited Soap Factory, Jeddah |
Complete Electrical, Mechanical and HAVC Systems to the new factory |
Unit Construction Limited/ Binzagr Lever Ltd. |
7.2M |
1986 |
Binzagr Lever limited Soap Factory, Jeddah |
Thermal Insulation Work |
Binzagr Lever Limited |
1.0M |
1986 |
National Guard Workshop |
Installation of Electrical, Mechanical and H.V systems in three locations |
Taylor Woodrow International Ltd. |
0.4M |
1986 |
Al Sulaimania Shopping Center, Jeddah |
Supply and Installation of Complete HVAC System including package A/C Unit Duct Works and Associated Electrical Services |
Freyssinet SA Ltd. |
4.0M |
1986 |
British Embassy, Riyadh |
General Electrical and Mechanical Works |
Foreign and Commonwealth Office, UK |
1.7M |
1987 |
Saudi Electrical Appliance Factory, Jeddah |
Complete Electrical and Mechanical Systems for New Factory |
Saudi Wiemer & Trachte Ltd. |
2.9M |
1987 |
Al Sorayai Carpet Factory, Jeddah |
Mechanical System for New Factory |
Sahara Building Contractors Ltd., Jeddah |
0.6M |
1987 |
British Embassy, Riyadh |
General Electrical/Mechanical Works Including Maintenance of Air Conditioning Equipment |
Foreign and Common Wealth Office, UK |
0.5M |
1987 |
SAVOLA (Saudi Vegetable Oil Company) |
Mechanical Services |
Saudi Vegetable Oil Company (SAVOLA) |
0.6M |
1987 |
Jeddah Oil Refinery Co (JORC) |
Replacement of corroded steel vessel support structures and associated E&M works |
Jeddah Oil Refinery Co (JORC)-Jeddah |
0.6M |
1987 |
Pre-commissioning Services for the SCADA Project |
Field Commissioning of the SCADA System throughout the Eastern Province. The works include instrumental calibration, loop checks, RTU checkout and remedial repairs of associated equipment and installation of new and replacement SCADA equipt. |
ARAMCO, Dhahran |
12.0M |
1988 |
Jeddah Oil Refinery Co. (JORC), Jeddah |
Supply and Installation of Overhead Cable Trays |
Jeddah Oil Refinery Co. (JORC)- Riyadh |
2.0M |
1988 |
Best Foods Production Facility (MAZOLA) Yanbu |
Complete Electrical, Mechanical and HAVC systems to the new factory and Admn. Building |
Best Foods Saudi Arabia Ltd. (MAZOLA) |
7.5M |
1988 |
Gold Factory, Jeddah |
Electrical, Mechanical and HAVC services for new factory |
Hussain A Saklou Est, Jeddah |
1.0M |
1989 |
Iraqi Embassy and residence, Riyadh |
Electrical, Mechanical and Plumbing Services |
Philipps Holzmann, Riyadh |
5.7M |
1989 |
Ministry of Defense & Aviation Jeddah |
8” N.B Fuel line from JORC to KFNB |
Ministry of Defense & Aviation, (MODA), Jeddah |
2.3M |
1989 |
Best Foods Production Facility (MAZOLA) Yanbu |
Electrical Process Installation |
Best Foods Saudi Arabia Ltd. (MAZOLA) |
0.6M |
1989 |
Al Khozama Center |
Dewatering Project. Supply, Installation and Commissioning of Pumps, risers, control system and cables |
Philipps Holzmann, Riyadh |
1.2M |
1989 |
GAZZAZ Show Rooms, Jeddah |
Electrical and Mechanical & HVAC Services for the Shopping Complex |
Freyssinet SA Ltd., Jeddah |
2.5M |
1990 |
King Khalid National Guard Hospital, National Intensive care Unit, Jeddah |
Electrical, Mechanical and Plumbing Services |
Saudi Wiemer & Trachte Ltd., Jeddah, Saudi Arabia |
2.6M |
1993 |
Mahmoud Saeed Glass Factory, Jeddah |
Mechanical and HVAC Services for Glass Factory |
Saudi Wiemer & Trachte Ltd. |
12.0M |
1993 |
Project Eseher, Lever Arabia Ltd, Jeddah |
Detergent Factory. Electrical, Mechanical and Instrumentation Services and process installation works |
Lever Arabia Ltd., Jeddah |
20.0M |
1994 |
Project Oasis, Binzagr Walls, Dammam |
Ice Cream Factory. Electrical, Mechanical and Instrumentation Services |
Binzagr Walls, Dammam |
21.4M |
1995 |
Refrigeration and Freezer Plant |
Supply and installation of Mechanical and Electrical Works |
National Refrigeration Company, Riyadh |
4.4M |
1999 |
MCBC- New Pharmaceutical Plant |
HVAC, Electrical, Instrumentation, purified water distribution and handling and installation of Pharmaceutical Machines |
Taylor Woodrow International/ Teamwork Saudi Arabia Ltd. |
58.8M |
1998 |
Electrical Installation for New Plant |
Electrical Installation of New Equipment and New Silo Plant |
Adwan Chemical Industries Co. Ltd., Riyadh |
1.0M |
2003 |
Installation of New Platformer Heater and New Coalescer Vessel and Hot Receiver Drum at Jeddah Refinery |
Erection and Installation of a New Cylindrical Heater Y13-F-06 in Jeddah Platformer Unit. Installation of New Coalescer Vessel and Hot Receiver Drum Y-02-D206 Modification Works in CDU #2 at Jeddah Refinery |
Saudi Arabian Oil Company (Saudi Aramco) Jeddah |
0.6M |
2003 |
Engineering Services for GSM Project |
Cellular network design, Network performance improvement and optimization, frequency planning |
Ericsson, Saudi Arabian Branch – STC |
3.0M |
2003 |
Al-Rajhi Industrial Laundry |
Plumbing and Process Piping |
Al-Rajhi International Contracting Co., Riyadh |
0.13M |
2004 |
Engineering Services for GSM Services |
Cellular network design, Network performance improvement and optimization, frequency planning |
Ericsson, Saudi Arabian Branch – STC |
5.4 M |
2004 |
SEC Power Plant 5 Riyadh |
Fire Fighting Network for Tank Farm |
METSCCO, Riyadh |
0.25 M |
2005 |
Engineering Services for GSM Services |
Cellular network design, Network performance improvement and optimization, frequency planning |
Ericsson AB Saudi Arabian |
7.2 M |
2005 |
Complete HVAC Works including Supply & Installation of 8 Chillers, RTR Pipes etc. |
Khursaniyah Industrial Support Facilities, Saudi Aramco |
Client Saudi Aramco |
18.5M |
2006 - 2008 |